The Polish KSC Act says what you must implement, not in what order. This plan splits the work into 6 phases. For each one we give a rough duration, who runs it, the legal basis, the evidence it leaves behind and how you run it in Regwolf.
The plan assumes a company the Act covered on 3 April 2026 that starts without an information security management system (ISMS; system zarządzania bezpieczeństwem informacji, SZBI) and must implement the obligations of chapter 3 of the KSC Act by 3 April 2027 (art. 33(1) of the amending act). If you already have ISO 27001, phases 2 to 4 will be shorter: start with The KSC Act and ISO 27001. What the Act itself requires is covered in the guide NIS2 in Poland: what the KSC Act requires of you.
Before you start
Three decisions before week one:
- Who decides. The head of the entity decides on preparing, implementing and overseeing the ISMS, plans the budget and assigns tasks (art. 8d KSC Act). Where the head is a board, name the person responsible; otherwise all its members are (art. 8c(2) KSC Act).
- Who does the work. An internal unit responsible for cybersecurity, or a contract with a managed security service provider (art. 14 KSC Act, more on providers).
- Who works on art. 8 and 11 tasks. Each such person first presents information from the National Criminal Register showing no conviction for offences against the protection of information (art. 8f(1) KSC Act). Request it now: without it, or a security clearance (art. 8f(3) KSC Act), you cannot let the team start.
The timeline at a glance
| Phase | Weeks | Run by | Output |
|---|---|---|---|
| 1. Foundations | 1–2 | Head of the entity, person responsible for security | Written classification, application for registration filed, ISMS scope, roles |
| 2. Gap analysis | 2–4 | Person responsible for security, IT | A status for every requirement and a list of gaps |
| 3. Risk and roadmap | 4–8 | Person responsible for security, control owners | Risk register, risk treatment plan and roadmap approved by the head of the entity |
| 4. Policies and documentation | 6–12 | Person responsible for security, document owners | Approved policies and normative documentation, acknowledgements |
| 5. Measures and evidence | 8–16 | IT, control owners, HR | The art. 8(1) measures in place, with evidence for each |
| 6. Check and maintain | 16–18, then ongoing | Internal auditor, head of the entity | Internal audit, management review, a plan for the next year |
About 18 weeks in total, because phases 3, 4 and 5 overlap. That is a rough figure for a company of 50 to 250 people. With one person responsible for everything and no outside help, plan for closer to 6 months.
Phase 1: foundations (weeks 1–2)
Goal: you know whether the Act covers you and as an essential or an important entity, the application for registration is filed and the ISMS scope is set.
- Assess whether the Act applies to you and record the assessment: the sector in Annex 1 or 2, size with partner and linked enterprises, class (art. 5 KSC Act). Our “Does the KSC Act apply to you?” test helps.
- Apply for registration in the list in the S46 system (art. 7c KSC Act) if nobody has yet. The application includes a statement by the head of the entity made under criminal liability (art. 7c(5) KSC Act). Details in registering in S46.
- Set the ISMS scope: the information system used in the processes that affect the provision of the service (art. 8(1) KSC Act). List the services, processes, locations and systems it includes.
- Assign roles: the person responsible for the ISMS, owners of the key areas and at least two contact persons; micro and small enterprises and important entities that are public entities appoint at least one (art. 9(1)(1), 9(2) and 9(3) KSC Act).
- Schedule the head of the entity’s training for this calendar year (art. 8e KSC Act).
Evidence after the phase: the written classification, confirmation of the application, the scope description, the head of the entity’s decisions appointing the roles.
You fill in the Company profile (Setup): sector, headcount, turnover. From it the ISMS scope screen (Governance) suggests a NIS2 classification, which you confirm, and shows the NIS2 / KSC Act deadlines: registration, the chapter 3 obligations and, for an essential entity, the first audit. You record the registration date there. You assign roles and their holders on the Roles and People screens, and management approves the appointment by decision; when a board member has no account, you record the signed resolution.
Phase 2: gap analysis (weeks 2–4)
Goal: you know which requirements of the Act you already meet, which partly and which not at all.
- Go through the art. 8(1) requirements: risk assessment, the 14 groups of measures in point 2 (a) to (n), threat information, incident handling and the measures in point 5 (the art. 8 checklist). Add the obligations outside art. 8: documentation (art. 10), incident reporting (art. 11–12c), contact persons (art. 9), the head of the entity’s training (art. 8e) and criminal record checks (art. 8f).
- For each requirement, record its status and how you will prove it. “We have it” without evidence is a gap.
- Check two points companies tend to miss: continuous monitoring (art. 8(1)(2)(g)) and physical security with access control (art. 8(1)(2)(c)).
Evidence after the phase: a dated assessment, the status of every requirement, the list of gaps.
On the Frameworks screen (Setup) you run the NIS2 assessment. Some answers are pre-filled from the company profile, and you can stop and finish later. When you complete it, every requirement on the Requirements screen (Audit & reports) has a status and a baseline you measure progress against. Some requirements of the Act that are not in the Directive, such as access to S46 or a reporting channel for the users of the service, are in the programme as controls of their own.
Phase 3: risk and roadmap (weeks 4–8)
Goal: the gaps are ordered by risk, each has an owner and a date, and the head of the entity has approved the plan.
- Adopt a risk assessment method (art. 8(1)(1) and (2)(a) KSC Act): scales, acceptance criteria, review frequency.
- Assess the risks to the system in the ISMS scope and decide how you treat each: reduce, transfer, avoid or accept.
- Assign controls to owners. You choose measures in proportion to the risk (art. 8(1)(2) KSC Act).
- Build the roadmap: first the gaps behind the highest risks and in areas with a statutory deadline.
- Get the head of the entity’s approval for the risk treatment plan and the roadmap. These are their decisions within the meaning of art. 8d KSC Act.
Evidence after the phase: the method, the risk register, the risk treatment plan, the roadmap, the head of the entity’s dated decisions.
You keep risks on the Risks screen (Risk): inherent risk, residual risk after controls, treatment and review date. The Risk treatment plan cannot go for approval while a risk above the risk appetite has no complete treatment or valid acceptance. Controls and their owners are on the Controls screen, and the order of work is in the Roadmap (Program). Management approves the plans by decision, and every decision goes into the decision register.
Phase 4: policies and documentation (weeks 6–12)
Goal: the required policies and procedures are approved, in force and known to staff.
- Prepare the art. 8(1)(2) policies: the risk assessment and information system security policies (letter a), the cryptography policy (letter k), the access control policy (letter n), the procedures for assessing the effectiveness of measures (letter h) and the cyber hygiene rules (letter j).
- Prepare the operational procedures: incident handling (art. 8(1)(4)), business continuity, contingency and recovery plans (art. 8(1)(2)(f)), software updates (art. 8(1)(5)(b)).
- Bring the documentation under control as art. 10 KSC Act requires: access for authorised people only, protection against loss, version marking, retention for at least 2 years after withdrawal (security documentation).
- Approve and publish, then collect acknowledgements from the people each document concerns (art. 8d(4) KSC Act).
Evidence after the phase: approved document versions with date and approver, version history, acknowledgements.
The Documents screen (Program) shows which documents NIS2 requires and which you do not have yet. You create a document from a template (for NIS2 also in Polish), write it yourself or import it. Each has an owner, an approver, a review period and versions. The published version is sealed, and edits to a draft leave the version in force untouched. Staff acknowledge in My policies or through an e-mail link, and you see who has not done so yet. Nothing changes a document by itself: when a template or the company profile changes, the owner is notified and decides.
Phase 5: measures and evidence (weeks 8–16)
Goal: the measures in the roadmap are in place, and every requirement has current evidence.
This is the longest phase, and you run it in several areas at once:
| Area | Provision | What to put in place |
|---|---|---|
| Incidents | art. 8(1)(4), art. 11–12c | Classification, the path for the early warning within 24 hours, the notification within 72 hours and the final report within a month of the notification (if handling is still ongoing: a progress report, and the final report within a month of the end of handling, art. 12b; an important entity that is a public entity submits only the notification, art. 12c), access to S46 (significant incidents) |
| Monitoring | point 2(g) | A continuous monitoring system covering the system in the ISMS scope, with a response to alerts |
| Access and identity | point 2(l) and (n) | Multi-factor authentication, granting and reviewing access rights |
| Assets and vulnerabilities | point 2(m), point 3, point 5(b) and (d) | An asset inventory with owners, updates, response to vulnerabilities |
| Suppliers | point 2(e), art. 8(2) | A list of ICT suppliers and an assessment of each |
| Business continuity | point 2(f) | The plans and their first test |
| People | point 2(d), (i), (j), art. 8e, art. 8f | Staff training, the head of the entity’s training, criminal record information |
| Users of the service | art. 9(1)(2)–(3) | Information on cyber threats and a channel for reporting incidents |
Evidence after the phase: at least one current piece of evidence for every requirement: a configuration, a register, a test record, an attendance list, a log.
On the Integrations screen you connect the systems Regwolf collects evidence from, such as Microsoft 365, Google Workspace, AWS, Okta or CrowdStrike Falcon. Each connector collects only what its card describes. You upload the rest on the Evidence screen (Program), where it waits for a person to approve it. Manual tests with a due date, and automated tests run at each sync, are in Control tests. Requirement status recomputes with each new piece of evidence, and every 6 hours Regwolf checks the programme and reminds you of reviews.
You record an incident on the Incidents screen (Risk). When you classify it as significant, the 24-hour and 72-hour deadlines run from detection and the one-month deadline for the final report from the notification. If handling takes longer, Regwolf sets the progress report deadline and counts the final report from the date you record as the end of handling. For an important entity that is a public entity, Regwolf sets only the notification deadline. A reminder arrives before each deadline. Regwolf drafts the report from the incident’s facts. You submit it in S46 and record the date and time of sending in Regwolf. A personal data breach has its own 72-hour deadline. You keep suppliers, their questionnaires and agreements in Suppliers, plans and tests in Business continuity, assets in Assets, and training, the head of the entity’s included, in Training.
Regwolf does not replace the continuous monitoring system required by art. 8(1)(2)(g) KSC Act. It collects evidence that such a system works, for example Microsoft Defender alerts or device status in CrowdStrike Falcon.
Phase 6: check and maintain (weeks 16–18, then ongoing)
Goal: you know whether the ISMS works, the head of the entity has reviewed the results, and maintaining the ISMS has its own plan and dates.
- Run an internal audit against the art. 8(1) checklist. Record each finding that shows a nonconformity as a nonconformity with a corrective action and a date.
- Assess the effectiveness of the measures using the procedure required by art. 8(1)(2)(h) KSC Act.
- Hold a management review: the head of the entity reviews the audit results, risks, incidents and progress and takes decisions for the next period.
- Plan the art. 15 security audit if you are an essential entity: the first by 3 April 2028 if your company met the criteria on 3 April 2026 (art. 33(2) of the amending act), otherwise within 24 months of meeting them (art. 16(2) KSC Act); then at least once every 3 years. The auditor cannot be someone who carries out tasks under art. 8 or art. 9–13 KSC Act for you, or did so in the year before the audit started (art. 15(2a) KSC Act, security audit).
Evidence after the phase: the internal audit report, the nonconformity register, the management review minutes with decisions.
Under Audit & reports you run the Internal audit with a frozen checklist, Nonconformities with corrective actions and an effectiveness check, and the Management review with inputs gathered from the programme and minutes approved by the chair. On the Requirements screen you seal a snapshot of the programme and share it with the auditor for 7, 14 or 30 days. An agent drafts reports for the board, and you send them.
After implementation: recurring obligations
| What | How often | Basis |
|---|---|---|
| The head of the entity’s training | Once per calendar year | art. 8e KSC Act |
| Risk assessment | Systematically, per your method | art. 8(1)(1) KSC Act |
| Business continuity plan test | Per the test plan | art. 8(1)(2)(f) KSC Act |
| Effectiveness assessment of measures | Per the procedure | art. 8(1)(2)(h) KSC Act |
| Change of the data in the list | Within 14 days of the change | art. 7c(3) KSC Act |
| Security audit (essential entity) | At least once every 3 years | art. 15 KSC Act |
In Regwolf, the Outstanding screen gathers what waits for you and your team: risk reviews, expiring evidence, acknowledgements, training and incident deadlines.
Key takeaways
- Implementation splits into 6 phases: foundations, gap analysis, risk and roadmap, policies, measures and evidence, check.
- Phases 3 to 5 run partly in parallel; together about 18 weeks, and companies the Act covered on 3 April 2026 have until 3 April 2027.
- Each phase leaves evidence: the authority may require an essential entity to prove it meets art. 8(1) (art. 53(2)(6) KSC Act).
- The head of the entity approves the scope, the risk treatment plan, the roadmap and the policies, and trains once a year.
Not sure yet whether the Act applies to you? Check with the tool “Does the KSC Act apply to you?” See where you stand today with our free NIS2 readiness assessment. Want to walk through the plan with us? Book a 30-minute demo.
Sources: the Act of 5 July 2018 on the National Cybersecurity System (ustawa z dnia 5 lipca 2018 r. o krajowym systemie cyberbezpieczeństwa; consolidated text in ISAP, in Polish) and the Act of 23 January 2026 amending the Act on the National Cybersecurity System and certain other acts, referred to here as the amending act (ustawa nowelizująca; Dz.U. 2026 poz. 252, in Polish). The timeline is indicative and is not legal advice.
Frequently asked questions
How long does implementing the KSC Act take?
The Act sets deadlines, not a duration: entities that met the criteria on 3 April 2026 implement the obligations of chapter 3 of the KSC Act, the ISMS included, by 3 April 2027 (art. 33(1) of the amending act). The plan in this article assumes about 18 weeks for a company that starts without an ISMS and runs phases 3 to 5 partly in parallel.
Where do you start implementing the KSC Act?
With the assessment of whether the Act covers you and as an essential or an important entity, and with the application for registration in the list in S46 (art. 7c KSC Act). Only then do you set the ISMS scope and run the gap analysis.
Can you implement the KSC Act without ISO 27001?
Yes. The Act requires no certificate and no particular standard, only an ISMS that ensures what art. 8(1) KSC Act lists. ISO 27001 makes the work easier but does not cover every requirement of the Act, for example continuous monitoring.
Who runs the implementation in the company?
The head of the entity takes the decisions (art. 8d KSC Act) and remains responsible for the obligations after entrusting them to another person (art. 8c(3) KSC Act). The work is usually run by the person responsible for information security with an internal unit, or by a managed security service provider (art. 14 KSC Act).
Does an important entity go through the same phases?
Yes, with one difference: the periodic security audit under art. 15 KSC Act applies to essential entities. The authority can order an important entity to carry out an audit by decision, for example after a significant incident.
The law is stated as at 19 November 2026. We prepared this article carefully, but some topics are summarised. It is for information only, is not legal advice and does not replace an analysis of your organisation's situation. Regwolf is not liable for actions taken or not taken solely on its basis.